The Case for Underfloor Air Conditioning:
The environmental and cost benefits examined
|
|
Glan Blake Thomas
Advanced Ergonomic Technologies, Ltd.
|
This paper aims to demonstrate the financial benefits and improvements in user efficiency as a result of using floor based systems, compared with the use of VAV and Fan coil Systems.
These buildings stand out because they are the first "super buildings" to adopt the concept of The Hiross Flexible Space System, and they both offer a chance to study the issues that form the basis of this paper. |
|
Current technology in the construction industry is under scrutiny by leading developers and construction companies simply because the costs of construction are high and time taken to build these buildings is considered to be too long.
In London and worldwide many professional teams are being asked to carry out value engineering studies in an effort to reduce cost and time. However many of these studies are confined to initial cost savings without necessarily investigating ways to save costs in ownership through life-cycle studies. Why? The answer is obvious: because developers want to maximise their return. In my opinion the flaw in this approach is that the teams look to make savings in each individual discipline instead of analysing the co-ordination of disciplines. They fail to fully embrace changes in working practice and the demands of modern office technology that demand a different type of building, as well as the demands of users, who are now far more aware of the need for efficient facilities in order to operate effectively in world markets.
Occupiers are now far more aware of the disadvantages imposed on them by poorly designed buildings and they are increasingly prepared to pay a premium for buildings that can show positive operational advantages.
An additional factor is that even in Hong Kong, buildings are now expected to last many more years than they were in the early 1980,s and it is not unrealistic to expect buildings constructed today to have a 40 to 60 year life span. This single factor begs for consideration of the total life cost considerations, which in turn demands a fully flexible and intelligent design, and must place additional emphasis and consideration of the costs of reconfiguration and operation. |
AT&T recently published the figures that show the proportion of costs for a typical building over a forty year life span to be in the order of:
The impact of such cost saving decisions often dramatically affects the reconfiguration and operational costs adversely and thus may push up the costs of reconfiguration by several percentage points. Currently initial cost saving practices are still general practice because the extra costs of such decisions are passed on to the as yet unknown tenant and are thus not a penalty to the developer, albeit a penalty to the nation.. If then design teams could be permitted to embrace the additional dimension of reconfiguration cost saving, and if developers could market this benefit effectively to the potential users, those developers may find that they can rent the building at a premium due to the added value of their design and thus improve their return by sharing part of the users operational cost saving over the life of the building and in my opinion benefit greatly in commercial terms. I think in time to come we will see government incentives for such endeavour. |
|
My area of interest is in the savings that can be made in the cost of reconfiguration and interestingly concept we employ to achieve dramatic savings in this area also offer a major saving in the initial cost. This is not a wild claim. For example, it is currently supported by; The Swedish National Pension Fund, British Airports Authority and other prestigious professionals including quantity surveyors, consultants and developers in many countries.
The concept is basically very simple.
Increasingly, buildings worldwide are adopting the concept of raised access floors for the intelligent distribution of power and data cabling. The wireless office in my opinion is still a dream imagined by data engineers and amusingly accommodated by power engineers and thus I think raised floors will become increasingly more used for some considerable time. However the general acceptance of the advantages that a raised floor offers for power and data has generally been overlooked by air conditioning and ventilation engineers who continue to argue for clear space in the false ceiling for distribution ductwork in the case of VAV and location of fan coil units. Times are changing though and now Leading consulting engineers and pioneering developers in many countries are already using this raised floor for many services including wave guides, central vacuum cleaning systems, air conditioning and displacement ventilation to great advantage. |
|
The Flexible Space System is basically an under floor air conditioning system making use of the floor void directly as a plenum for the distribution of air. The raised floor
Because a false ceiling is not required, often the building can have 11 floors in the height otherwise required for ten.
Alternatively the system can operate using a HIVAR in place of a CAM unit. There
are a number of differences demonstrated in the air flow diagram.
What we can see is that with a velocity of around 2m/s underfloor and with a design flow temperature of 14deg C we can happily operate with a CAM unit placed in the centre of a 30 m zone. However if we allow the velocity to drop to 0.3m/s we see a dramatic increase in temperature pick up and consequently a reduction in the size of zone possible. Hence Variable Volume systems applied to underfloor plenums can have serious problems with temperature pick up by the time the air has travelled to the perimeter of a space where it is needed to do the cooling particularly in low load situations. As a general rule of thumb we try not to exceed twenty metres. |
Birds eye view of a flexible space installation
Chilled and Heating water are delivered to the CAM by means of small diameter pipe work and condensate water is drained away to nearby risers.
Fresh air may be delivered directly to the CAM from outside or via a central ventilation system. Extract air is usually taken away at high level in the space near risers.
Let into the floor over supply plena are individually controlled Fan terminals of either recessed or floor standing configuration. These terminals introduce air into the space above, in accordance with the dictates of their own on board controls system. Each unit has fan speed and temperature set point adjustment and through a fast data link may be controlled from a central point. In a recent survey in London, 78% of office workers polled requested personal control of their environment as a priority.
![]()
Return air grilles are positioned in the floor over return plena to permit the return of spent air to the CAM unit for re-conditioning.
The whole system is controlled by means of the electronic management system and Hiromatic advanced controller. All CAMs and Fan terminals can be connected into the system permitting centralised monitoring and control of various functions to take place. This may also be integrated with a Building Management System subject to compatibility and requirements.
![]() |
|
Conventionally engineers will ask for perhaps 500mm or 600mm clear under structural beams for distribution ductwork on buildings with perhaps 2000m2 floor plate or greater.
The aspect ratio of ductwork and the problems of drumming and support make a 3:2 ratio generally the norm.
Making a total of 3800mm to an average 4000mm Now if we consider doing away with the false ceiling completely we can reduce the height by 600mm. If we then consider using the raised floor for ventilation as well as power distribution we must increase the floor void to provide a cable zone and a ventilation zone and we have found that generally a total 300mm void offers all the space that a building ever requires. Thus we find a net saving in height of approximately 450 mm.
![]() This equates to somewhere between 10 and 15 % of the height of a building and we must study the inherent savings that are achieved as a direct and indirect result of utilising the floor void in this way.
|
|
British Airports Authority recorded a 25% reduction in construction time by using this concept on two 6000m2 projects. Such a dramatic difference in programme time offers huge savings in financing costs and permits the developer to earn rental income sooner.
![]() |
|
The Swedish National Pension Find are on record as having saved 5% to 7% of the construction cost at the Alvik Strand development also confirmed by BAA at Gatwick and Stansted. The two major areas of saving come from:
1. The savings in the curtain walling materials and all other vertical structural elements due to the height saving and In Hong Kong this saving in cost could have amounted to around 6.5 million dollars or 65 dollars per sq m of which some 5 million dollars was saved on Curtain walling alone, the rest being in reduced vertical components including vertical structural elements, lift shafts, stairwells, risers.
Builders generally agree that any solution that permits them to "Get out of the ceiling quicker" reduces management and time and often reduces damage to final finishes, which can also be very costly.
Architects find reduced "snagging problems" and Engineers report reduced commissioning programmes. For example: At the Rover Design HQ in Gaydon, 7 weeks saved on commissioning programme)
|
|
Firstly the reduction in building programme offers huge savings in the total interest charge on the development. A 20 week reduction in programme could offer perhaps $US 5 000 000.00 saving in interest charges on a 100 000 sq m development
Secondly and still of considerable note the nature of a floor based system permits delivery of key mechanical and electrical elements far later in the programme and in some cases permits the equipment to be supplied at the time of the tenant fit out and thus cash flow and cash demand can be improved, offering savings in interest charges on the development. Taking 20% of the contract to be mechanical and electrical services and perhaps 50% of that element to be purchased 3 months later in the program could offer a further 2.5 million dollars saving. |
| Earlier release of the building permits letting to take place earlier. In Hong Kong rental is approximately $30/sq ft per year. Taking 50% of the space to be released early the increased rental revenue for 20 weeks equates to nearly 6 million dollars. |
|
Because the raised floor is used as a plenum for air distribution, in many countries the floor is regarded as equipment rather than fixture and thus attracts capital allowances. Furthermore if the floor is deemed to be equipment then anything sitting on the floor is also deemed to be equipment and so partitions, modular power, desks, chairs and carpet are all deemed to be equipment and all attract increased capital allowances.
Normally tax relief/capital allowance stands at 25%. The Capital allowance on a building of 100 000m2 would be 1.5 million dollars and if we consider the average fit out costs of partitioning to be around $200 dollars per linear m we could expect capital allowances on partitioning within the building to at least double the tax relief. |
| Building Simulation Ltd were commissioned by a leading UK developer to study the difference between VAV and the Flexible Space system at Falcon House in Hounslow, and showed a marked 26% reduction in energy and CO2 emissions. |

|
These figures are supported by other studies, for example The Swedish Clinic for Occupational Medicine investigated Indoor Air Quality at Alviks Strand and reported that the Flexible Space System had significantly improved the quality and comfort of the indoor environment with air quality results for all parameters proving to be well below the maximum recommended values for a healthy environment.
The system makes use of the floor void directly for the distribution of air and thus that air becomes in contact with the concrete slab. Using off peak power tariffs the building manager can run the plant at night and reduce the cost of power, while he cools the thermal mass of the building by a few degrees. This permits the generated cooling load the following day to be absorbed into the slab and thus reduces the demand on the chillers for several hours each day. Roger Preston and Partners have carried out a computer simulation of this night time cooling performance and find that even with minimum ventilation, considerable energy saving is possible.
|
|
Tenants immediately find reduced time in the initial fit out of their space permitting them to start their business operations earlier.
In a report to a Facilities Management conference in Strasbourg the General Manager of Panasonic in Paris reported the results he found in comparing his original building served by ceiling based fan coil systems with his new head quarters building served throughout with the flexible space system as follows. Panasonic results In the first year of operation the Facilities manager estimated that he relocated 70% of his work stations to suit changing management ideas and requirements. Direct invoiced costs of change:
Original Building With Fan Coil System $170-$200/m2 Building with Flexible Space system $17-20/m2 Net saving in cost of change in the order of $167/m2/annumTime for reconfiguration: Building With Fan Coil System 12-16 weeks Building with Flexible Space system 1 week The savings simply in the cost of reconfiguration equate to the cost of the rent in many offices. In Hong Kong applying these figures the savings to the tenants in the first year could amount to 15 million dollars. This equates to approximately half the rent in this city centre building. The reduction in time taken is immeasurable in terms of the increase in staff productivity but is recognised to be very significant by leading organisations. |
|
Who was it who said, "there are lies, damned lies and then there are statistics"
The figures above may only be used indicatively but what they tell us is that by giving serious consideration to selection of building services we can as engineers offer a major contribution to the well being of our nations economy.
If we add up all the savings mentioned above we find that the following
Even if we divide the Panasonic findings in half the savings made by the tenants year on year will pay back the average construction project in around 10 to 12 years. With the average life of buildings at 40 to 60 years we can expect the choice of underfloor air conditioning to offer a construction payback in the order of 4 to 5 times. I believe these figures to be conservative and further I believe that they are so important that no developer can afford to ignore at least the investigation of such advantage on every project. It is the responsibility of cost consultants to fine tune and verify the actual costs on each occasion. I believe that the above brief paper offers at least an insight into the implications of poor decision making at the beginning of a project and I believe this information makes a valuable contribution to the subject of "Intelligent Building" or as I prefer to call it "Building Intelligently"
| ||||||||
|
|
![]() |
|
|